Day 21 of the Debmar Atlantic 2024 Project - Another Friday, more sign-offs

Yesterday at work there was some decent success!

In the picture here you can see myself on the left, the Vessel Deleagte - 3rd Engineer Dwayne, Clint from IQS and the Quality Controller and George... ok... you can just see the top of his hard hat...

There he is! George, the MCM Technician doing the Chiller service.

We were all there to sign off that the Chiller circuits have passed a holding vacuum test and as you can see in the picture above that the Guage shows a nice 2.98mbar. Our target was to remain under 5mbar.

Thus, everyone is happy to proceed to the next stage!

Here is some more in action pictures if anyone ever wonders why our overalls get so dirty. On the floor, crawling in to the underside of the chiller to reach a valve. This is just something that needs to be done!

Now with this Chiller signed off on the pressure and vacuum stages, we have charged both circuits of the chiller with a holding Charge of Refrigerant.

We are getting somewhere...

Till tomorrow...

Cheers!
@zakludick

Hive South Africa



0
0
0.000
11 comments
avatar

Congratulations @zakludick! You have completed the following achievement on the Hive blockchain And have been rewarded with New badge(s)

You published more than 2000 posts.
Your next target is to reach 2100 posts.

You can view your badges on your board and compare yourself to others in the Ranking
If you no longer want to receive notifications, reply to this comment with the word STOP

Check out our last posts:

Feedback from the November Hive Power Up Day
Hive Power Up Month Challenge - October 2024 Winners List
Be ready for the November edition of the Hive Power Up Month!
0
0
0.000
avatar

Nice! 2000 posts!

!LOL

0
0
0.000
avatar

Congrats on 2k posts !

0
0
0.000
avatar

Thanks!

Need to go do another 2000 posts now... then I will be a 10th of the to 40k posts...

0
0
0.000